The perfect storm

When did current procurement practices fall out of favour, asks James Cash, and will clients and industry seize the opportunity to enact their transformation?

For shipwrecked mariners, the custom of the sea was the unwritten convention that starving survivors in a lifeboat might draw lots to determine who survives and who – by feeding their shipmates – were to die. For centuries, this grisly custom was both recognised and accepted in broader society, with the surviving mariners tacitly pardoned. All of this changed in 1884 following the case of R v Dudley and Stephens (two of four survivors from the shipwrecked yacht Mignonette who had killed and consumed a comatose shipmate), which found that necessity was no longer a defence of murder. 

This change in public and legal opinion seems just as relevant today as the construction industry continues to experience its own perfect storm of revelations, not least in relation to the survivalist model of procurement that has predominated in recent decades.

Evidence that the procurement eco-system is distressed is compelling. Top-tier suppliers race to the bottom on price in order to win business to the detriment of those further down the supply chain, creating their own risks of insolvency. Profits and liquidity are consumed by over-competitive cost-cutting at every level as suppliers gnaw away at each other’s profits. And clients continue to incentivise these models of behaviour by overly relying on the cheapest option as an indicator of best value.

At its worst, this leads to poorer outcomes, including substandard and potentially unsafe buildings, unhappy tenants, and a financially distressed and demoralised construction industry. It’s unsustainable and there are no long-term benefits for anyone.

So, have we finally reached a point where these visible and tangible defects in the procurement process have become unpalatable to the industry and society at large? Will a sea change in behaviour follow and what could that look like?

Richard Harral, Technical Director at CABE, says: “I think we’re at a tipping point where we have to make some very conscious decisions about whether to carry on as we have done for decades or start to invest in changing our approach to procurement and value.

“I’d argue very strongly that continuing to procure as we have done is unacceptable and ultimately not in the interest of anyone in the development chain. That includes clients, consultants, contractors and residents.”


Procuring for value

The Construction Leadership Council’s Procuring for Value report urged clients to change their mindsets about value. With relatively small changes in approach and behaviour, they could reap significant productivity gains across the construction sector. It urged the industry, clients and government to work together to establish a whole-life integrated sector to improve performance, end-user satisfaction and deliver broader societal benefits through higher-quality buildings.

Observing that the current approach is highly transactional, the report said there was little motivation for designers, contractors and suppliers to engage with each other at an early stage of a project or take an interest and learn from the building once it is in use. All parties were, therefore, destined to repeat mistakes. They fail to adopt best practice, the result of which is buildings that do not meet the needs and expectations of the people that live and work there.

Procurement systems, the report said, need to align the objectives of multiple project stakeholders to create the most significant value. The UK government’s Industrial Strategy Whitepaper in 2017 introduced the balanced scorecard that requires procurers to consider relevant social and economic objectives, such as skills development, diverse supply chains and sustainability, as well as cost-effectiveness.

However, while the scorecard is a useful starting point for a new definition of value, many in the industry consider it is still too broad and open to interpretation. And currently it acts as a tick-box exercise to go through, rather than a project enhancing tool.

By developing an industry-wide definition of value that takes into account more than the initial capital cost, the industry can produce a universal methodology for procurement and promote shared and consistent standards across the industry.  

The industry also needs to work with the Infrastructure and Projects Authority (IPA) to develop cost and performance benchmarks for assets and suppliers. Creating an industry dashboard that is regularly updated will enable the industry to demonstrate it has increased capacity, productivity and reduced negative environmental impacts. 

The report also recommended establishing an end-user rating system for built assets to help monitor how the people living and working in them view those assets. Meanwhile, developing a cross-industry prequalification process would reduce bureaucracy from the procurement system.


Downward spiral

The procurement process is currently trapped in a vicious circle. Complexity and under-performance in the construction industry often push clients to fixate on the lowest capital cost as the only indicator of value. However, lowest capital cost models of procurement create a system that suppresses costs in a way that distorts contractor and supplier business models.

Construction businesses respond by cutting costs to stay competitive, but not by improving productivity or efficiency (as should happen in a genuinely competitive market). Instead they marginally chip away at quality. Poor outcomes follow; poor-quality assets that often involve higher maintenance costs over the life of the building. Dissatisfaction with the quality of the outcome reinforces the client’s view that if they cannot guarantee the quality of the build, they should pay as little as possible, which perpetuates under-pricing to win work. So the downward cycle continues.

“The evidence is clear that this approach is not working,” Harral says. “Tier one contracting is increasingly unprofitable and unviable. Do we need any better evidence than the collapse of firms such as Carillion to recognise that cost suppression has gone too far?”

The signs are that the sector’s predominant business models are not just unsustainable but potentially unsafe. There are also compelling indicators that it is damaging the people who work in the industry. According to a report by the Chartered Institute of Building, 26% of construction industry professionals thought about taking their own lives in 2019. It’s a factor that can only have increased as a result of Covid-19 and the lockdown.

Harral says: “The human cost of bad procurement to the construction industry itself – in mental health and physical health terms – is both unsustainable and unjustifiable. The stress experienced by people working in an over-competitive market remains one of the key reasons for construction’s critical skills shortage. If clients want a more skilled, stable and competent workforce, they need to think actively about how their approach to procurement can support a better working environment.”

Meanwhile, with an ever-increasing focus on climate change, the construction sector needs to be more capable of designing and delivering buildings that perform as predicted. While legislation, such as the Building Safety Bill, aims to have a positive impact on the industry, it should also prompt client bodies to think differently about procurement activities and their development process.

“When you drive costs down in construction, it’s not like shopping online and getting price comparisons,” Harral notes. “Ultimately the product changes to reflect the price that’s paid. Where you’re getting that lower price, someone is taking less time, taking less profit and less margin. They are changing something or doing things differently. That’s fine if the innovation is sound, but it can also mean poorer quality, or safety or durability.”

What then are the solutions that will lead to a significant change in procurement?

Harral says: “Firstly clients must move away from the lowest capital price as a primary metric of success, to an approach that focuses on ensuring that projects are reasonably costed and that the supply chain and all the way down can make a reasonable profit. 

“An unprofitable sector cannot deliver the safe and sustainable buildings we need; and it cannot improve to deliver genuine improvements in efficiency and productivity that can lead to meaningful reductions in cost and programme, which will help meet housing supply targets.”

35 istock

Perceptions of value

A critical factor in improving the procurement process involves redefining clients’ perception of what value is.

In July 2018, the government published the Construction Sector Deal, and the report of the Public Administration and Constitutional Affairs Committee, which determined that the collapse of Carillion was due in part to the government’s procurement policies. In response, the Construction Leadership Council (CLC) published Procuring for Value, setting out recommendations for creating a sustainable business model for the entire supply chain.

The author of the report, Ann Bentley, is a CLC member and global director at international cost management and quantity surveyor Rider Levett Bucknall. She says there are several factors inhibiting clients from taking a value-led approach right now. Further research showed clients didn’t have common standards and there was also a lack of knowledge. 

“There were often tough time and annual budget pressures. People didn’t want to be the first to do it. And in some places, there was a conviction that lowest price gives the best value, even though the evidence tells us that isn’t the case.

“We came up with some solutions to this. Such as having a more common definition of what value is, and enhancing the competence of practitioners, particularly in advisors, so that they could talk about value. People need real evidence about value, as opposed to rhetoric.”

This could include a consistent digital platform to capture and analyse the information that is coming in. The Construction Innovation Hub now has funding to develop a suite of tools that will help define the value profile for a given project because value is a different thing according to different projects for different clients. Bentley says these tools will guide clients through the individual delivery models and commercial strategies needed to ensure the delivery of what is genuinely best value.

“It will also provide a benchmark facility against which you can forecast and measure performance. And that’s forecasting performance through the design period, and then measuring performance during the occupation period. If that’s tied in with the commercial models, it would give you incentives for the whole of the supply chain that will help you to deliver value on your projects.”

Instead of just looking at finance, clients can consider a whole range of different values that might come to play on a project. Clients can discern what is most important to them and identify where value accrues on a project to establish a value profile that can be converted into a value index.

Bentley says: “Instead of just tendering on the basis of price, you can tender against this value index. Not only will you be looking at price, but other factors such as the competence of contractors and designers, and also the human value of the actual building they’re going to deliver. Clients will be able to compare suppliers on a properly benchmarked index and pick the ones that present the best value to them.

“Value can be defined. It’s not easy, but it’s not impossible. With the sort of target that we’re developing at the hub, it will give everybody tools to create a value baseline. And I think it will be a game-changer in terms of how value can be delivered.”

Better collaboration will improve outcomes

Once clients are able to compare a wider range of outcomes, rather than reacting on basic capital cost, the argument for better forms of procurement become self-evident. Harral says: “Client bodies need to understand that it is impossible to generate real efficiency and productivity gains in projects where the tender price is less than the real cost of completing the work. If those gains are achieved, it is most likely at the expense of something more valuable in the medium- to long-term.

“And if the economic arguments on their own are insufficient then regulation and increased integration of ethical values at strategic level must also be used to compel necessary change.”

In addition to a more formalised value definition and benchmark system there are several other useful tools that can provide better certainty in the delivery of projects, while also ensuring realistic expectations are established about the progress of the project at an early stage.

Harral says: “There needs to be a shift to the use of alliancing and collaborative forms of procurement to support integrated design and construction supply chains. There are many good examples of how this can be achieved, but uptake remains low.”

Alliancing

The use of alliancing and partnering in construction and infrastructure projects are not new and was a key element of the 1998 Egan Report, Rethinking Construction. 

The concept involves two or more organisations working together to improve performance through agreeing on mutual objectives, devising a way for resolving any disputes and “committing themselves to continuous improvement, measuring progress and sharing gains”.

The thinking behind partnering is to depart from a traditional construction approach, based on arm’s length commercial and contractual relationships and onerous contract terms. It involves active management of all aspects of the project, as opposed to reactive management of putting things right when issues arise and depend on personal commitment and trusting relationships. 
The collaborative relationship involves sharing the risks and resolving problems throughout the life of the project.

“Flexibility underpins the alliance model,” says Paul Walsh partner at Hill Dickinson, “which allows the contract and parties to adapt easily to the changes to address complex design, construction and environmental issues that may not be evident at the outset of the project. This is perhaps the key advantage of the alliance model.”

Clients and contractors expect change and innovation in delivery timescales with the focus on outcome as opposed to the process, which may affect timings and budget. The alliance model works on a unified agreement under which all parties share the benefits and risks. This is different from the traditional contracting model where each party operates under its own separate contract containing separate objectives.

Walsh adds: “Any gain or pain is linked with good or poor performance overall and not to the performance of individual parties. The idea is to create an integrated structure whereby multiple suppliers work together under one central alliance to deliver the project as a whole.”

The collaborative framework has a set of shared values leading to unanimous and principle-based decision-making, ideally supported by several good-faith obligations such as co-operation and communication between the parties.

sheffield hallam

Sheffield Hallam University campus masterplan 

In June 2020, Sheffield Hallam University announced it had appointed three partner suppliers to form the Hallam Alliance to deliver the university’s new campus plan. The Alliance is described as a ground-breaking new construction industry procurement and delivery model, tipped to inspire change in the construction industry procurement. The Alliance comprises the university, design-consultancy BDP-Arup, construction firm BAM and facilities management specialists CBRE.

The university announced a 20-year development framework for the Sheffield Hallam estate and went out to tender to create an alliance who will be involved throughout the entire project. The alliance approach encourages a shared ethos of partnership, collaboration and innovation to bring about more effective and efficient developments. The first phase could see £220m invested over the next five years focused on the university’s city centre estate.

The partnership will share profits and losses to ensure that all parties work efficiently. The Hallam Alliance is one of the first adopters of NEC4 Alliance Contract (ALC) operating under a governance structure with formal cooperative boards which require unanimous agreement, making decisions on issues on a best-for-project basis.

The contract is designed for use on major projects and programmes of work where longer-term collaborative ways of working are to be created. It can also be used to deliver a programme where several lower-value projects can be combined to create a major programme of works.

Paul Cleminson, Construction Director at BAM, which is behind ten current higher education buildings, says: “This new type of framework means the clients, designers, construction contractors and FM providers all have the same goals and objectives, with benefits such as a transparent, open-book costs approach and improved risk management. This builds mutual trust, which will then drive efficiencies, standardisation and the continuous improvement we are all seeking.”

Integrated project insurance (IPI)

Similar to alliancing, IPI aims to align the interests of all parties with the functional needs of the client, helping to create a culture of collaboration. IPI collectively insures the client and all other alliance partners, including consultants, specialists, manufacturers, construction managers and their supply chains. It replaces the liability-driven professional indemnity insurance with financial loss cover where the overrun costs exceed a specific level determined by the policy.

IPI has been a long time in the development, first conceived in Sir Michael Latham’s report in 1984, and reiterated in the Egan report in 1998 and subsequent efforts to reduce the adversarial and fragmented nature of contracting arrangements. In 2008, Constructing Excellence told the government select committee on business and enterprise that too often insurance included: “redundant layers of consultant, contractor and supplier cover which often do not protect the client”. 

There is also a lot of waste. The committee heard as much as “£1bn was wasted every year on insurance cover that provides for the same types of risk”. Insurance brokers Griffiths & Armour also calculated that for every £1 paid out in professional indemnity claims £5 had been spent in legal fees. Under a single policy, the need for litigation is significantly reduced. 

IPI aims to improve and encourage integrated teams and remove the barriers to achieving integration. One of those barriers is the liability culture and the insurances that are fragmented to mirror an older fragmented construction industry.

When you have many different parties protected by many individual insurances, the policies don’t provide overall protection. Procurement sets people at each other’s throats from the beginning, and the separate insurances can accentuate the problem because they encourage the shifting of blame onto the other players.  

IPI is a single policy taken by the client and will cover the client and all the members of the team. It protects against the risks that were typically covered by contractors’ all-risks and third-party or public liability policies. It will also cover the risks usually covered by public indemnity policies but won’t cover it in quite the same way. It tends to cover the cost of the project – the cost plan – so that if there is a problem on the project and it causes the cost plan to overspend it will cover some of that, avoiding a lot of legal and forensic costs of pinning the blame.

There is a pain and gain share to the integrated team, and if all parties are working closely together it is in the interest of all members to ensure mistakes, defects and overruns do not arise. 

It is also an opportunity for some contractors in the supply chain to be part of large projects where previously they could not accept the degree of liability that prime suppliers needed to pass down. 

IPI, therefore, can have an impact that goes beyond the top-tier contractors. Helen Tapper, President of the Finishes & Interiors Sector (FIS) says: “I’m convinced that integrated project insurance will help accelerate genuine supply chain partnerships, real collaboration and a pipeline approach that will provide an opportunity to invest in off-site and the people we need.

“A move towards project insurance will start to ensure that risks are clearly thought through from the outset, throughout. And we move away from the build and design culture that we find ourselves in. A more project-based approach with risk management will reduce the risk in construction and enable companies to think beyond the next project.”

Dudley College

Dudley College of Technology

Among recent projects that have successfully embraced the collaborative approach, Dudley College of Technology is an exemplar. IPI has been used twice by the college based in the West Midlands. The first on its £12m Advance II construction training centre project designed by Metz Architects; and second on the £26m Institute of Transformational Technologies designed by Cullinan Studio currently under development.

The Advance II block was the first official government trial project for IPI. The aim was to shave 30% off the construction programme and deliver a capital cost saving of up to 20% by giving all parties ownership of the design decisions and contribute to decisions that balanced risk and resources.

In September 2014, Dudley College published the procurement notice, setting out expectations on IPI. Shortlisted bidders then took part in team-based behavioural workshops to assess which firms would be best capable of forming an alliance. In May 2015 the six key players – the client, the contractors Speller Metcalf and Metz Architects, Fulcro, H&H Architectural and Derry Building Services – signed an alliance contract binding each into a virtual company.

With a contingency fund of £1m, IPI gave the college a guaranteed cost of what their liability would be if the job went wrong. The project cost overrun liability is limited by a combination of pain/gain mechanism. In this instance, a cost overrun of up to £500,000 on the agreed target build cost of £10m would be shared among the alliance, with overspend above £10.5m paid out through the insurance policy. Meanwhile, any savings up to 7.5% of the budget would be shared among the alliance members.

A paper published by Reading University based on an in-depth study of the project claimed: “Advance II, under IPI, has broken new ground in project procurement, organisation and delivery and demonstrated considerable benefit from collaborative working among the key project participants. The project has achieved many notable successes and has generated valuable learning for future applications of IPI, as well as for collaborative project working more generally.

“The collaborative strength of the alliance has been tested by important developments on 
Advance II, notably during detailed design and construction when it emerged that the Target Outrun Cost might be exceeded and, later, when the agreed completion date came under threat. It is a testament to the robustness of the IPI model that both the Alliance Contract and IPI Policy remained unchallenged through the process; and also that the collaborative commitment among the Alliance prevailed and helped to identify solutions founded on the collective approach to risk and reward sharing.”

Two-stage book tendering

In two-stage tendering, the contractor is first involved in increasing cost certainty and enhancing the construction process in an advisory capacity before the scheme is fully designed. Typically, the contractors will submit a price for assisting the client in designing the building, together with a schedule of rates – used to value the scope of works where the final nature or quantities are not yet known – that in the second stage will be used to form a fixed price for the complete works.

Jonathan Parker, national framework manager, Pagabo says: “Historically, the two-stage route has been the most popular within the construction industry, but in recent times the single-stage process has gained in popularity.

“The shift occurred because property teams are under increasing pressure to manage costs and need full visibility of these at the earliest stage. However, by doing this, they are losing the potential development flexibility and added value that comes with the collaborative two-stage process.”

At the second stage, the pre-contract process is complete. The contractor enters into a detailed contract negotiation with the client, which will include price, programme and contract conditions. The client and their teams will collaborate with the chosen contractor to design and develop the whole project. At this stage, they create a bill of quantities, a final price and final contract with the contractor.

The advantages of this approach are that it brings in contractors/subcontractors in at an early stage of the project, helping them to deliver a more practical and buildable design, with fewer costly problems to resolve on-site during construction or to rectify after the build. Such early engagement tends to lead to improvements in the practicalities and affordability of the design, and construction methods reducing financial and time costs.

Like the other initiatives discussed, two-stage tendering can lead to a more collaborative project team and help identify significant risks early. Likewise, stakeholders can spot and share opportunities earlier in the process and develop them with more chance of success. Like IPI, this collaborative approach can lead to pain/gain-style agreements and the more successful the scheme is all parties benefit.

However, two-stage tendering is often suited to projects that are more bespoke and complex where early contractor engagement is essential to assist in finalising a design and ensure efficiencies on-site in terms of time and cost.

Time and tide

Time and tide

The industry needs to change now, particularly if it is to avoid similar pricing pressures, caused by the financial crises as the economy recovers from Covid-19. Risks will only increase if a client’s choice of procurement pathway remains predicated on an assumption that lowest cost is best value. It’s time to recognise that in perusing lowest-cost models, clients are effectively driving the supply chain to feed on each other to remain solvent.

Procurers will need to put more time and resource into scoping out their projects, as Bentley says: “They should genuinely understand what things cost before they go out to tender. Many clients often don’t know what the costs are, they don’t know what is realistic, they just know what is cheapest.”

Meanwhile, contractors must look for more collaborative working that bridges the gaps between on-site, and off-site; design, build and facilities management. They must look for early-stage engagement to help their clients accurately price projects in a way that delivers sustainable benefits for all. Only then will procurement no longer feel like drawing straws in a lifeboat. 

Image credit | Simon Pemberton | iStock | Alamy

Jobs

Contract

Senior Quantity Surveyor

Senior Quantity surveyor Are you an experienced Senior Quantity Surveyor looking for your next cha...

Permanent

Senior Building Surveyor

We have an exciting opportunity for an experienced Building Surveyor / Senior Building Surveyor to ...

Permanent

Graduate Building Surveyor

We are currently recruiting for a Graduate Building Surveyor to join one of the most respected prope...

Permanent

Senior Quantity Surveyor

My client, a highly reputable Utilities company, recognised for the design, build and maintaining of...